Opening of the CHRISTINE 11th
meeting in Riga, Latvia
Maris Andins
JSC LatRailNet
Facts and numbers about Latvia to warm up
1/3 of the total population (0,65 of 2 million) live in capital (Riga)
One of the oldest languages in Europe still spoken
Consumer prices approx. 35-42% lower than in Brussels,
London, Rome and Paris
More than 1/3 of Latvia is covered by forest
500 km of white sand beaches, 12 000 rivers and over 2 000 lakes
Collection of over 300 000 traditional folk songs
7th fastest internet speed
78 liters of beer per capita consumed yearly
High rate of fashion models per capita,
average women are taller than ladies of any other nation
7th highest percentage (45,7%) of women in managerial positions of
business companies
Welcome to Riga
Amazing Art Nouveau and other architecture
from various times and political regimes
reflecting history of 800 years
Must see places in Riga
House of Blackheads, Monument of Freedom, Dome square,
TV Tower, churches and golden roosters on top,
riverfront of Daugava and more…
… and more
… massive
Central Market
of Riga
… open-air
etnographic museum
of traditional Latvian
lifestyle
We love to sing and dance
Riga is the host of traditional
song and dance
festival with 40 000
participants
Taste Riga
Riga Black Balsam, black (rye) bread
and local Latvian beer
Railway sector in Latvia
Facts (2016):
• 1859 km operational length of all lines (248 km suburban electrified)
• 16.5 million total train-kilometres
• 47.8 million tonnes annual freight volume (-14%)
• 17.2 million passengers carried (+1%)
• 3 freight and 2 passenger operators
• highest freight transport modal split in EU
Freight volumes
2016 total freight volume – 47,8 million tonnes (14,0% decrease)
21,8
21,3
20,1
19,1
16,6
15,9
1,8 1,8
1,7
1,13 1,3 1,4
1,1
0,3
2014 2015 2016
Oil and oil products Coal Minerals Black metals Chemicals
Organisational structure
• infrastructure manager (Latvian Railway - LDZ) and freight / international passenger operator
(LDZ CARGO) both inside the state-owned railway concern
• independent charging and allocation body (AS LatRailNet) - subsidiary of the concern (LDZ)
About the organizer
• Part of SJSC Latvian Railway holding, separated independent company
• Established in 2010
• 29 employees
• Performer of essential functions of the IM:
- Decision-making on train path allocation
- Determination and collection of the charges
• Independency requirements set out in Railway Law
About the meeting
• CHRISTINE + PRIME
• significant TAC related railway industry event
• 20+ countries represented
Meeting venue
WiFi network access
WiFi hotspot: RadissonBlu Daugava
Free access (without password)
Meeting agenda
September 20 (day one) September 21 (day two)
Working session
Introduction part
Other topics and conclusions of CHRISTINE
Working session CHRISTINE & PRIME joint session
Direct costs, charging systems and current
TAC Differentiation tools status of legal framework
Working session
PRIME session 1
Market segmentation and mark-ups
Working session
PRIME session 2
Factors affecting track maintenance costs
Agenda: September 20 (part 1)
9:00 – 9:30
Welcome coffee, Hotel Radisson Blu Daugava
9:30 – 11:40
Introduction part
- Presentation of participants
- Organizational instructions
- Latvian Railway presentation
Discussions on agenda
11.40 – 12.00
Coffee break
12:00 – 14:00
Working session: TAC Differentiation tools
- Benchmark TAC 2018 [presented by ÖBB]
- Changes in TAC system [presented by HŽ Infrastruktura]
- Noise differentiated TAC [presented by BAV]
Discussions: Does differentiation of the infrastructure charge give incentives to RUs?
14:00 – 15:00
Lunch, Hotel Radisson Blu Daugava restaurant
Agenda: September 20 (part 2)
15:00 – 16:40
Working session: Market segmentation and mark-ups
- Ramsey-Pricing and price elasticities [presented by ÖBB]
- Market segmentation and mark-ups in freight [moderated by BAV]
Discussions: Has IM to meet maintenance requirements or to meet user needs?
16:40 – 17:00
Coffee break
17:00 – 18:30
Working session: Factors affecting track maintenance costs
- UIC documents usage in cost allocation [presented by ProRail]
- Comparative analysis of factors affecting track maintenance costs [presented by LatRailNet]
Discussions: Who or what incurs costs that are not directly incurred as a result of operating the train?
18:30 – 19:30
Logistics for the evening
19:30
Dinner, Fazenda Bazārs restaurant
Logistics for the evening
Meeting point: RadissonBlu lobby at 18:45!
Agenda: September 21 (part 1)
9:00 – 9:30
Welcome coffee, Hotel Radisson Blu Daugava
9:30 – 11:40
Working session: Other topics and conclusions of CHRISTINE
- German TAC system and experience with the regulatory body [presented by DB-Netz]
- Network area [presented by LatRailNet]
- Conclusions of the CHRISTINE session and next venue
Discussions: Information exchange between CHRISTINE, PRIME and Commission [moderated by ADIF]
11:40 – 12:00
Coffee break
12:00 – 14:00
CHRISTINE & PRIME JOINT SESSION:
Direct costs, charging systems and current status of legal framework
- Presentation of Estonian railway and Charging scheme [presented by TJA]
- Presentation of Lithuanian railway and Charging scheme [presented by LG]
- Presentation of Serbian railway and Charging scheme [presented by DR]
Discussions: Does common rules means endogenous results?
14:00 – 15:00
Lunch, Hotel Radisson Blu Daugava restaurant
Agenda: September 21 (part 2)
15:00 – 16:40
PRIME session I
- Introduction, expectations and plans [presented by Alain Quinet, Maria Álvarez and Sian Prout]
- Implementation of the rules (EU Law) on direct costs and related problems [presented by Frank Jost]
16:40 – 17:00
Coffee break
17:00 – 18:30
PRIME session II
- Compatibility with EU laws [state of play and discussion]
- Conclusions of the PRIME session
18:30 – 19:00
Logistics to the museum
19:00 – 20:00
Excursion to the Latvian Railway Museum (Optional)
20:00
Farewell
Logistics for the railway museum
Meeting point: RadissonBlu lobby at 18:45!
Meeting coordinator
Feel free to contact in case of any questions:
Eriks Pjatkins
Event head coordinator
JSC LatRailNet Assistant manager
phone: +371 20394650
e-mail:
[email protected]
or find on web:
www.lrn.lv/christine/contact/
Thank you for your attention!
for more info visit www.lrn.lv/christine
Distinctions meet!
Justina HUDENKO
JSC LatRailNet
TAC Differentiation tools
Time frame: 12:00-14:00
Presentations:
• Benchmark TAC 2018 [ÖBB]
• Changes in TAC system [HŽ Infrastruktura]
• Noise differentiated TAC [BAV]
Discussions:
Does differentiation of the infrastructure charge give incentives
to RUs?
Differentiation tools
• Most popular: reservation charges; performance scheme;
ETCS/ERTMS
• Not in use: investment projects based
• 6 countries use only 1 or 2 differentiation tools
• 7 countries use 3 or more differentiation tools
Does differentiation of the infrastructure charge give
incentives to RUs?
Market segmentation and mark-ups
Time frame: 15:00-16:40
Presentations:
• Ramsey-Pricing and price elasticities [ÖBB]
Discussions:
• Market segmentation and mark-ups in freight [BAV]
• Has IM to meet maintenance requirements or to meet user
needs?
Regulation on segmentation
• Full IM/AB responsibilty in 7 countries
• Regulator’s or state’s approval required in 3 countries
• 1 country has clear provision in the legal framework
• 3 countries are in the development process
Segmentation pairs used or expected
• Most popular outside mandatory one:
• combined transport vs direct trains;
• urban vs regional;
• block train vs SWL
• Almost all segment pairs are in use!
• 4 countries use only 1 or 2 segments
• 9 countries use 3 or more segments
Regulation on mark-up level
• Full IM/AB responsibilty in 8 countries
• Regulator’s or state’s approval required in 3 countries
• 1 country has clear provision of target revenue in the legal
framework
• 1 country is in the development process
Market segmentation and mark-ups in freight
Factors that have impact on MCB in freight:
• Political relations
• Market activities of other transport corridors
• Cooperation among logistic chain members and internal
competition
• Transportation time and other competitiveness factors
• Industries competition and world demand on transported
cargo
Institutions involved in rail financing (1)
state state state
Forwa Conse Forwa Conse Forwa Conse
rder gnee rder gnee rder gnee
a) b) c)
state state state
state state
Forwa Conse Forwa Conse
Forwa Conse
rder gnee rder gnee
rder gnee
d) e) f)
Institutions involved in rail financing
and financing instruments (2)
• Government in 6 countries
• Ministries in 6 countries
Has IM to meet MS maintenance
requirements or to meet user needs?
The progress of indicative strategy and multiannual
contract
EXPECTED CHANGES
Multiannual contract
IN PROCESS
Indicative strategy
IN FORCE An approach used for the incentive
regulation of the costs base level?
other
15% stimulation stimulation of IM
of IM
39% regulation
regulation other
46%
Factors affecting track maintenance costs
Time frame: 17:00-18:30
Presentations:
• UIC documents usage in cost allocation [ProRail]
• Comparative analysis of legal frame and other factors
affecting TAC benchmark [LatRailNet]
Discussions:
• Who or what incurs costs that are not directly incurred as a
result of operating the train?
Implementation of the Directive
2012/34/ES and the related Regulas
other transposed
8% into the
national
legislation,
but the
Schemes are
transposed not in force
into the yet
national 38%
legislation
and are in
force
54%
TACs based on new Schemes are going to be introduced:
Assets and renewals
Progress of assets register Assets evaluation method
current
values
is developed 38%
in progress 46%
54% historical
values
62%
Renewal costs calculations:
econometric marginal cost analysis
forecasted depreciation costs
direct allocation to track lines
renewals are not included in the direct costs
laid down by government
depreciation multiplied by CATRIN elasticity
modulations
Direct costs
20% of full cost
appr. 1 EUR per train-km
1,315 EUR per train kilometre
2.84 (with noise bonus EUR -0.82/km)
approx. 30% for maintenance and renewal 15% of full costs
2,435 € per train kilometre Not yet known
55% of the total cost
Borders of minimal access package
and charging parameters
product specifics
gross weight
train km
curves
number of wagons
axle load
type of train gross tkm ticket revenues
train path specifics
neto tkm
speed
line parameters
Service facilities
No common position on who is responsible for
access conditions to service facilities
Responsible entity IM RU OSF other
Cross-border information exchange 38% 54% - 8%
Cargo clearance, delivery of cargo
- 92% - 8%
to customers
Customs clearance of freight
8% 69% - 23%
transport
Commercial examination of wagons 23% 69% - -
Train designation 23% 62% 8% -
Assembling or disassembling of
Almost all agree that charging of trains
8% 69% 15% -
service facilities owned or managed by Transferring of rolling stock for
loading/ unloading or to the related - 85% 8% -
IM is responsibility of IM or ChB sidings
Wagons maintenance and renewal - 77% 23% -
Wagons preparation for loading - 85% 15% -
Other issues
No common position on reasonable Collection of charges is mostly
profit calculations or no profit responsible to IM, some
calculations at all exceptions in case of ChB
Almost all have contractual agreements No common practice on RMMS
between IM and RU conduction: Regulatory body,
Ministries, IM, RUs and
unknown persons J
Logistics for the evening
Start from lobby 18:45!
Other topics and
conclusions of CHRISTINE XI
Time frame: 9:30-11:40
Presentations:
• German TAC system and experience with the regulatory body
[DB-Netz]
• Network area [LatRailNet]
• Next venue
Discussions:
• Information exchange among CHRISTINE, PRIME and
Commission [moderated by Adif]
Who should be the holder
of the CHRISTINE website?
Opinions on administrative rights are divided equally:
only one administrator vs each country has rights!
volunteer for several years
don't support the idea at all
other
25%
LatRailNet as a successful creator J CHRISTINE
community
41%
Holder rights
change
annually with
hosting
organization
17%
CHRISTINE
most countries agree to share expenses: non-profit
organization
in easy way and not expensive 17%
Restrictions
benchmarking objects are sensible
depending on the source and content
not relating to TAC-issues
joining organizations is
a complex process
can only publish on internet
information that is already
published
Voting on name and structure
christinegroup (christine-group) 6 votes
6 countries gave one vote per different name
No common position on extension
Brief well structured participant's profile and
TAC system description
Both topical & chronological
CHRISTINE meetings’ material storage;
topical storage of external publications on the TAC issue
No forum and galleries
simple and practical common platform
to share and store information
Conclusion
holder a community → christinegroup.notcom → fees on voluntary basis →
one administrator volunteer per webpage + possible to post announces for registered users →
simple structure
States participants CHRISTINE Current mailing list TAC related Participants posts as
•Common structure meetings •State information a main page
•Brief legal position •Chronological order •Company •Topical order (indexed •No storage
•Link to TAC, network •Links to .ppt and •Names by participants) •RSS or subscription if
statement and other minutes protected if •Mails •Scientific publications necessary
relevant documents necessary •Possibility to send and deliveries
•Next venue (non common e-mail •Legal documents
editable or link) •.ppt of CHRISTINE
and other working
groups or conferences
CHRISTINE & PRIME
Time frame: 12:00 – 14:00
Presentations:
• Presentation of Estonian railway and Charging scheme [TJA]
• Presentation of Lithuanian railway and Charging scheme [LG]
• Presentation of Serbian railway and Charging scheme [DR]
Discussions:
• Does common rules means endogenous results?
Deliveries of CHRISTINE
to PRIME and Commission
Thank you for your attention!
for more info visit www.lrn.lv/christine
LATVIAN RAILWAY GROUP OF
COMPANIES
20.09.2017
Two infrastructure spaces
2
Latvian Railway Group
3
Latvian Railway at a glance
4
Freight Transportation Volumes
(million tons)
5
Passenger Transportation
(million people)
6
Awards and Rankings
7
Industry Impact on the Economy
8
Latvian railway map
9
Major Investments (EU 2007-2013)
10
Projects: 2014 - 2020
Railway network electrification (stage I)
Modernisation of Section Sarkandaugava – Mangali –
Ziemelblazma in Riga Railway Network
Reconstruction of Daugavpils Marshalling Yard
Construction of Daugavpils Reception Yard and Access Lines
Implementation of Railway Traffic Operation and Control Center
Modernization of Railway Passenger Service Infrastructure
11
Latvian Railway Electrification – 1st stage
Electrification of railway lines Daugavpils, Rezekne – Krustpils; Krustpils – Riga
12
Three more infrastructure development projects in
Riga and Daugavpils
13
Integration in Global Logistics Networks
14
THANK YOU!
15
Track Access Charges 2018
Results of international benchmark
by ÖBB-Infrastruktur AG
Katja Skodacsek
Network Access
Regulation Management
28th September 2017
Which Infrastructure Managers and
Allocation bodies were analysed?
2018
Preliminary remark:
This benchmark is based on
published Network Statements
and additional information
provided by infrastructure
Estonia managers until September 25,
Russia 2017.
Latvia As this benchmark has not been
Ireland
verified by all infrastructure
Lithuania
managers yet, it is still a draft.
Belarus
Ukraine
Moldavia
Romania
BIH Serbia
Monte- Bulgaria
negro Kosovo analysed
Macedonia
Albania not reviewed
Greece Turkey charges 2018 not published yet
Modification of charging structure in 2018
(minimum access package)?
2018 Modification *)
new charging structure has
been implemented 2017
no modification
no modification in structure, but
Estonia in price level
Russia
charges 2018 not published yet
Latvia
Ireland
not reviewed
Lithuania
Belarus
Ukraine
Moldavia
Romania
BIH Serbia
Monte- Bulgaria
negro Kosovo
Macedonia
Albania
Turkey
*) ÖBB-Infrastruktur AG:
Greece
due to an appeal new charging structure not yet
in force
Implementation RECAST/CIR up to 2018?
direct costs/mark ups
2018 Implementation RECAST/CIR in
Network Statement 2018
Switzerland has not implemented
the CIR 2015/909 into national law
Estonia through the land transport
Russia
agreement. However, the
Latvia regulations of the CIR are applied
Ireland
in wide parts of the national
Lithuania
legislations of the track access
charges.
Belarus
Remarks:
Ukraine
France: scheduled TAC 2018 have
not been approved by the French
Moldavia regulatory body. The TAC reform has
been postponed to 2019.
Romania
Spain: new charging structure has
BIH Serbia been implemented 2017
Monte- Bulgaria
negro Kosovo Lithuania: RECAST has been
Macedonia implemented, CIR methodology is
Albania prepared, with a request of phasing-in
Greece Turkey
ÖBB-Infrastruktur AG:
due to an appeal new charging
structure not yet in force
Market segments 2018
passenger
PSO freight TOTAL
non-PSO
long distance regional
due to an appeal new charging structure not yet in force
1 1 2 2 6
1 1 1 3
6 2 7 5 20
16 (by regional
5 5 26
authority)
1 4 5
1 4 5
12 (by regional scheduled TAC 2018 have not been approved by the French regulatory body.
2 + 17 (high speed) ? ? The TAC reform has been postponed to 2019.
authority)
3 1 1 5
2 2 (+ segmented by 4+
carried cargo type)
excl. empty runs and loco trains
Market segments: commercial passenger traffic (without PSO)
(referred to RECAST/CIR)
commercial passenger traffic
open access (international)
open access (national premium): HSL
open access (national premium): not HSL
on conventinal lines (day/night)
scheduled 2019
o on high speed lines (17 market segments per origin / destination)
excl. empty runs and loco trains
Market segments: long distance passenger traffic
(referred to RECAST/CIR)
long-distance passenger traffic in general
Metro Day (amount of charge depends on speed, time criterion)
Basic (no run between metropolitan stations/or high volume border points, time)
Night service (run between 11pm and 6am) add-on Express (very high priority)
Charte-/Nostalgia service
Point-to-point services (time and speed criterion)
Long distance services on variable gauge provided that at least 10% of
ist total route runs on Iberian gauge lines
Long distance services over long tansersal sections: routes longer than
700 km with no origin, destination or intermediate stop in Madrid or its
branches
other long distance services (excluding locos, empty trains)
transit/non transit
excl. empty runs and loco trains
Market segments: regional passenger traffic
(referred to RECAST/CIR)
short distance traffic high (seats >200, metropoltian area, time criterion)
short distance traffic low
hub node sprint (≥ 75 km/h, metropolitan area, hub stations)
hub node (< 75 km/h, metropolitan area, hub stations) add-on Holy (operation on sundays
and holidays)
ring node (metropolitan area, no hub station)
no node
federal state (load runs/empty runs)
PSO, urban and suburban services (entirely on a commuter hub), intercity
services (routes < 300 km)
by regional authority (12 market segments) scheduled 2019
Market segments: freight traffic
(referred to RECAST/CIR)
freight traffic (general)
single wagon load traffic
freight traffic manipulated
combined traffic
freight traffic non-manipulated block trains
corridor freight train
night (predominatly an night)
international freight service (predominately day)
national freight service TOP (predominately day, distance <100 km and ≥800 km)
national freight service BASE (predominately day, distance ≥100 km and <800 km)
very heavy train (>3.000 tonnes)
dangerous goods block-trains
add-on planning characteristic (Z-Flex, R-Flex)
Local freight train for dangerous goods (≤ 75km on a train path, max rake 370m, ≤3000t)
add-on operational characteristic (express, fast)
local freight trains (≤ 75km on a train path, max rake 370m, ≤3000 t)
standard
transit/non transit (segmented by cargo type)
excl. empty runs and loco trains
Price per train km 2018 (incl. catenary):
freight - wagon load transport 1000 tons
Remarks:
excl. empty runs
and loco trains
average TAC:
whole network and
volume-weighted
based on all
lines/segments
SBB incl. noise bonus -0,89 €
> 9 € in average
11,08
9,77
Price per train km 2018 (incl. catenary):
freight - block trains 1000 tons
Remarks:
excl. empty runs
and loco trains
average TAC:
whole network and
volume-weighted
based on all
lines/segments
SBB: incl. noise bonus -0,89 €
remark: >9 € in average
11,08
9,77
Price per train km 2018 (incl. catenary):
freight - intermodal trains 1000 tons
Remarks:
excl. empty runs
and loco trains
average TAC:
whole network and
volume-weighted
based on all
lines/segments
SBB: incl. noise bonus -0,89 €
Price per train km 2018 (incl. catenary):
passenger long distance trains 500 tons (high speed)
Remarks:
excl. empty runs
and loco trains
average TAC:
whole network and
volume-weighted
based on all
lines/segments
Price per train km 2018 (incl. catenary):
passenger long distance trains 500 tons (<160 km/h)
Remarks:
excl. empty runs
and loco trains
average TAC:
whole network and
volume-weighted
based on all
lines/segments
Price per train km 2018 (incl. catenary):
regional passenger trains 250 tons
Remarks:
excl. empty runs
and loco trains
average TAC:
whole network and
volume-weighted
based on all
lines/segments
Price per train km 2018 (incl. catenary):
urban passenger trains 250 tons
Remarks:
excl. empty runs
and loco trains
average TAC:
whole network and
volume-weighted
based on all
lines/segments
Changes
in Croatian Track
access charging
system
HŽ Infrastruktura
Network access
Dino Džafo
Minimum Access Package Charges formula
(as it was)
Minimum Access Package Charges formula
(as it was)
Minimum Access Package Charges formula
(as it was)
Train type is given by a train path equivalent (5 categories for passenger
transport, 4 for freight transport and 1 for locomotive trains)
additional charges for train mass (over 1500 tonnes) and the use of
tilting technique
Minimum Access Package Charges formula
(as it was)
Line is set by a technical line parameter, line operation equivalent and line
parameter costs equivalent (in total 6 line categories)
final value is set as a sum of individual line parameters multiplied by
their train path length
Minimum Access Package Charges formula
(as it was)
Basic price is determined on the basis of direct costs (for maintenance and
traffic management on railway infrastructure)
different prices for passenger and freight transport
Minimum Access Package Charges formula
(as it was)
Traction el. is given by direct costs (for electrical supply equipment maintenance
charge and realized train path kilometers with el. traction)
Minimum Access Package Charges formula
(as it was)
Price amounts to K = 1 when calculated in the amount of direct costs, but
correction Government may determine a lower correction coefficient
coefficient (depending on the situation of the transport market)
T – Train path equivalent
(as it was)
in passenger transport – is determined on the basis of the train mass by
correlating the average train mass of an individual grouping with the average
mass of all trains in passenger transport and on the basis of train category.
Equivqalent is increased regarding of train category:
20% for EuroCity, InterCity, express and agency trains
15% for fast and semi-fast trains
10% for passenger and cross-border trains
T – Train path equivalent
(as it was)
in freight transport – is determined on the basis of the train mass by
correlating the average train mass of an individual grouping with the average
mass of all trains in freight transport.
T – Train path equivalent
(as it was)
Additional charge for train mass [dm] - is applied on all types of trains in
freight transport whose mass is greater than 1500 tons and amounts to 0.30.
Additional charge for the use of tilting technique [dn] – is applied on all
trains in passenger transport which use tilting technique and amounts to
0.20.
L – Line parameter
(as it was)
Lines grouped in 6 categories based on traffic and
technological aspect.
L – Line parameter
(as it was)
Line cost equivalent
- unit cost of infrastructure for each line
Line operation equivalent
- 2 components (realized train kilometers and achieved gross tonne-kilometers)
Technical line parameter
- type of lines (share of double track lines in all lines)
- slope streaks (share of lines with more then 10 promils)
- speed of lines (100 km/h)
- electrification
- allowed load (less than 2ot per axis)
Train type & Line parameter
(changes & adjustments)
- traveled distance is added to train mass
- correlating average gross tonne kilometer
of an individual grouping with the average
gross tonne kilometer of all trains
(separately in freight and passenger
transport)
- use of total train mass
cvlkm – Basic price per train kilometer
(as it was)
Determined on the basis of direct costs for the maintenance of railway infrastructure
and traffic management on railway infrastructure and realized train kilometers.
Prices are expressed separately for passenger and for freight transport.
cvlkm – Basic price per train kilometer
(as it was)
Direct Determinated:
costs
Initially - 10% of Train Control (Rail operation) and 100% of
Use of Running Track Points and Junctions (Rail
operability)
Later on - 100% of Rail operation and 20% of Rail
operability
cvlkm – Basic price per train kilometer
(changes & adjustments)
Direct EU Regulation 2015/909
costs
include only costs that are triggered directly by the operation
of the train service
use of eligible costs
3 year average
K - Price correction coefficient
(as it was)
Price correction coefficient [K] – amounts to K=1 when the charges are calculated
in the amount of direct costs. The infrastructure owner (Government), depending on
the state of the transport market, may determine a lower correction coefficient.
K - Price correction coefficient
(changes & adjustments)
compliant with national legislation, but could go against the
general EU goals and principles of railway infrastructure charging
new approach to the direct cost calculation
use of share of eligible costs
canceled
in line with EU and national legal
framework
Minimum Access Package Charges formula
(new)
S – Coefficient for the single wagon load train
consultant’s proposal
Implemented for stimulation of RU`s for transportation single
wagon loads
is applied to all types of freight single wagon load trains and
amounts 0,8
S – Coefficient for the single wagon load train
Description increase of a rail freight transport competitiveness by means of transport of
and little amount of goods (transported by a few wagons)
advantages
prevention of a migration of significant part of rail freight transport to roads
and better track utilization
straighten up the competitive position of railway transport compared to road
transport.
Additional proposals from consultants company
&
future interventions
empty containers
a train carrying only empty containers is considered as train with
empty wagons (lower value of train path equivalent)
support of new transports
incentive for trains equipped with ETCS
According to the Directive 2012/34/EU, infrastructure managers should
modify the charging system through a temporary differentiation for
trains equipped with ETCS (in order to accelerate the installation of the
European Train Control System on board locomotives).
Thank you for your attention!
[email protected]
Schweizerische Eidgenossenschaft Federal Department of the Environment,
Confédération suisse Transport, Energy and Communications
Confederazione Svizzera
Confederaziun svizra Federal Office of Transport
Noise Differentiated
TAC in Switzerland
20.09.2017 Kjell Kolden
Federal Office of Transport, Kjell Kolden
20.09.2017, CHRISTINE XI, Riga
1
Topics
• Swiss legal requirements
• Noise bonus since 2002
• Evolution in numbers
• International cooperation
• Conclusions
Federal Office of Transport, Kjell Kolden 2
20.09.2017, CHRISTINE XI, Riga
Noise bonus – legal requirements
Federal noise abatement law (BGLE Art. 5)
Ø Silent railway vehicles will be given preferential
treatment with respect to the track access charges.
Federal Office of Transport, Kjell Kolden 3
20.09.2017, CHRISTINE XI, Riga
Noise bonus – evolution since 2002
2002: CHF 0.005/axle km
2004: CHF 0.01/axle km
2013: only freight trains - differentiated:
0.01 CHF/axle km
K LL 0.02 CHF/axle km
D 0.03 CHF/axle km
2020: Cast-iron brakes banned -> bonus quo vadis?
Federal Office of Transport, Kjell Kolden 4
20.09.2017, CHRISTINE XI, Riga
Noise bonus – evolution in numbers
Millions CHF 35
30
25
20
15
10
5
0
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
Federal Office of Transport, Kjell Kolden 5
20.09.2017, CHRISTINE XI, Riga
Noise bonus – internat. cooperation
Originally NL-DE-CH (Corr. 1); new: AT (ÖBB)
• Single Entry
Point (SEP)
Ø facilitate
applications
Ø enhance
retrofitting
Federal Office of Transport, Kjell Kolden 6
20.09.2017, CHRISTINE XI, Riga
Noise bonus – internat. cooperation
Database SWDB (100’000 silent wagons)
Federal Office of Transport, Kjell Kolden 7
20.09.2017, CHRISTINE XI, Riga
Conclusions – do you approve?
From our perspective (FOT)…
• Financial incentives work!
• Cross-border cooperation
improves the situation
• Less resources needed
thanks to automatization…
• …but data quality is crucial
• Cooperation with wagon
holders/owners = win-win
Federal Office of Transport, Kjell Kolden 8
20.09.2017, CHRISTINE XI, Riga
Ramsey Pricing / Elasticities
Survey among CHRISTINE members
by ÖBB-Infrastruktur AG, Network Access
August 2017
Elasticities & Ramsey
Elasticity: how responsive an economic variable is to a change of another?
E.g. train path charge in a given market segment is increased
à this may lead to higher tarifs for end customers
à therefore to a decrease of demand
Ramsey is a method, which uses a pricing inverse to the elasticity of the demand.
What parameters are needed?
§ elasticities
§ cost structure: percentage TAC of total costs of Railway Undertaking
Goal: to spread a given total revenue over market segments according to „what the market can bear“
Questions sent by email July 11, 2017
Questions
§ Do you apply Ramsey pricing in your charging system?
§ If you apply Ramsey pricing for determining TAC:
Which price elasticities are your market segments for 2018 (and for 2019) based on?
§ Are you aware of any studies in Europe / your own country regarding concrete data about the price
elasticities of market segments?
Could you possibly forward links, studies or extracts of studies concerning elasticity values?
Answer received
Estonia
Russia
Latvia
Ireland
Lithuania
Belarus
Ukraine
Moldavia
Romania
BIH Serbia
Monte- Bulgaria
negro Kosovo
Macedonia
Albania
received
Greece Turkey
not received
Principles for TAC 2018
Based on Ramsey and price elasticities
Price elasticities with Ramsey in use planned
Price elasticities without Ramsey in use planned
Finland
no elasticities
Norway
not reviewed
Sweden Estonia
Russia
Latvia
Ireland Denmark
No elasticities planned or implemented
United Lithuania
Kingdom
Belarus New elasticities model is planned | Ramsey will not be used
Netherlands
Germany Poland
Belgium No elasticities planned or implemented
Luxemburg
Czech
Ukraine
Republic
Slovakia New elasticities model is planned | Ramsey will be used
France
Switzerland Austria Moldavia
Hungary
Slovenia Romania No elasticities planned or implemented
Croatia
BIH Serbia
Portugal
New elasticities model is planned | Ramsey will not be used
Spain Italy Monte- Bulgaria
negro Kosovo
Macedonia Elasticities are implemented without Ramsey
Albania
Greece Turkey
Elasticities are implemented with Ramsey
Elasticities are implemented with Ramsey (due to an appeal not yet in force)
UIC leaflets in charge setting
Christine meeting
20 September 2017
Julianne Wormsbecher, ProRail
1
Question
Do you use UIC documents (e.g. 714 or 715) in your cost allocation
or charge calculation?
If so, could you shortly explain which information you use and how
you use this?
Answer: No
Answers from: Trafikverket, PLK, Adif, SŽDC, Infrabel, LatRailNet, SNCF
Réseau, Infraestruturas de Portugal, HŽ Infrastructura, Banedanmark
2
UIC leaflets 714 / 715
• Track classification
• Relation between maintenance costs and traffic load
UIC group Theoretical traffic load (Tf) Cost index (min / max)
1 130.000 < Tf 130 / 150
2 80.000 < Tf < 130.000 120 / 130
3 40.000 < Tf < 80.000 105 / 120
4 20.000 < Tf < 40.000 90 / 105
5 5.000 < Tf < 20.000 65 / 90
6 < Tf < 5.000 40 /65
3
Simplified / schematic
illustrations
Application by ProRail
1. Determining direct costs 2. Setting charge ratio
Cost index
Costs
Direct costs
1,25 1,58 etc.
1
Fixed costs
0-120t 121-160t 161-320t
Theoretical traffic load Weight category
Trainpath 2018 ratio charge
0-120 ton 1 € 0,8537
121-160 ton 1,25 € 1,0682
161-320 ton 1,58 € 1,3531
321-600 ton 2,21 € 1,8906
601-1.600 ton 3,55 € 3,0277
1.601-3.000 ton 4,27 € 3,6455
> 3.000 ton 4,63 € 3,9545
4
Discussion
Do you use train related charge categories for further differentiation of TAC,
e.g. weight classes, or
speed intervals, or
…?
Is this differentiation fully cost related?
If so, how do you determine the charges per charge category?
By using empirical models?
By using experts opinions?
…?
5
Appendix: Charging Parameters – IM’s TAC 2016
Source: PRIME-ENRRB Charging workshop, 3 February 2017 6
Track Access Charges DB Netz
CHRISTINE Meeting, Riga, September 21th 2017
DB Netz AG | I.NMK2 (T) | Matthias Fett
Concept of TAC 2018 discussed with market and applied – TAC
appoved by german regulatory body with adjustments
December November June October 6. February December
2012 2014 2015 2016 2017 2017
Directive Kick-Off Conclusion Public consultation Final decision by Implementation
2012/34/ EU Consultation with consultation & at regulatory body TAC 2018
market communication regulatory
advanced concept to body
market
1 Concept n Based on EU and german legislation development of a new infrastructure charging concept
and discussion with german regulatory body
2 Communication n Check concept for market compatibility and testing the concept
3 Implementation n Implementation of the final concept after the approval of the german regulatory body on
December 2017
2 DB Netz AG | I.NMK2 (T) | 21.09.2017
EU Directive 2012/34 defines common principles for
infrastructure charges
Basic logic according to EU Directive 2012/34
Basic elements
Costs directly incurred as a result of operating the train service (marginal
costs)
Costs directly incurred
n Each customer has to bear the costs which he directly causes
as a result of operating the train
service
Mark-up to cover full costs according to the ability to pay of the market
segment
n Remaining costs are divided among all users to maximise market demand
Mark-up to cover full costs n The level of the mark-up it is based on the ability to pay of the market
according to the ability to pay of segment and shall not exclude the use of infrastructure by market segments
the market segment n Necessary to secure sufficient funds to finance the infrastructure
Further elements (incentive components of behaviour control)
Further elements n Additional charges defined by the law reflecting e.g. the costs of
environmental effects, scarcity of capacity, investments…
3 DB Netz AG | I.NMK2 (T) | 21.09.2017
Segmentation of freight traffic is based on the
NEW
characteristic of the traffic
Does not depend on the number of
Loco train locomotives
Advance performance of a load
drive
Conventional train
Very heavy train
No local train, train without dangerous
Train weight > 3.000 t goods,
no heavy train
Local freight train
Train journey shorter than 75km
Dangerous goods train AND train shorter than 370 m
Train carrying only dangerous Local dangerous goods train
goods
Train journey shorter than 75km
AND train shorter than 370 m AND
train carrying only dangerous
goods
4 DB Netz AG | I.NMK2 (T) | 21.09.2017
Freight traffic charges
NEW
TAC 2018 – Charges [Euro/Trainkilometer]
Optional
Optional
Segment
Segment Direct costs
Direct costs Charges
Charges Z-Flex11
Z-Flex R-Flex11
R-Flex Fast11
Fast Express11
Express
Conventional train
train 1,315 2,83
2,83 -0,10 -0,10 +0,50 +2,00
Conventional 1,315 (2,98)
(2,98)
-0,10 -0,10 +0,50 +2,00
Very heavy
heavy train
train 2,337 4,05
4,05 -0,10 -0,10
Very 2,337 (4,00) -0,10 -0,10 // //
(4,00)
Dangerous goods
goods 1,315 3,46
3,46 -0,10 -0,10 +0,50 +2,00
Dangerous 1,315 (3,40)
(3,40)
-0,10 -0,10 +0,50 +2,00
Local freight
freight 0,818 1,67
1,67 -0,10 -0,10 +0,50 +2,00
Local 0,818 (1,64)
(1,64)
-0,10 -0,10 +0,50 +2,00
Local dangerous
Local dangerous goods
goods
0,818
0,818 1,88
1,88 -0,10
-0,10 -0,10
-0,10 +0,50
+0,50 +2,00
+2,00
train
train
Locomotive run
run 0,627 1,67
1,67
Locomotive 0,627 (1,64) // // // //
(1,64)
1Surcharge or discount
5 DB Netz AG | I.NMK2 (T) | 21.09.2017
Segments in long-distance passenger traffic are based on
Unmodified
three segmentation criteria
6 am – 8 pm* 8 pm- 11 pm** 11 pm – 6 am
Train connects Metro Day*** Basic Night
metropolitan
railway stations
Train does not Basic
connect
metropolitan
railway stations
Empty Run Charter-/Nostalgia Point-to-Point
Further segments
* 9 am to 8 pm at week-ends
** 6 am to 9 pm at week-ends
*** btw. 100 km/h and 160 km/h charges are based on average speed
6 DB Netz AG | I.NMK2 (T) | 21.09.2017
Long-distance passenger traffic charges
NEW
TAC 2018 – Charges [Euro/Trainkilometer]
Optional
Segment Direct Costs Charges
Express**
Metro Day 11,63
1,145 +2,00
>160* 11,31
Metro Day 5,07
1,145 +2,00
<100* 4,95
Basic 1,145 4,51 +2,00
4,41
Night 1,145 2,51 +2,00
2,46
Charter / 2,05
0,666 /
Nostalgia 2,46
Point-to-Point 1,145 4,08 /
3,99
Empty run 0,627 2,05 +2,00
2,46
7 DB Netz AG | I.NMK2 (T) | 21.09.2017
Segments in local/suburban passenger transport had to be
adapted to new national legislation – states as market segments
Requirements § 37 ERegG Adaptation of the local passenger transport concept
n States as market segments in local passenger n Dismissal of the former segmentation based on passenger
transport throughput of train stations and travelling time within the
market segment local passenger transport
n Average charges for local passenger transport
for every state have to euqal the average n New: One market segment per state
charges of the corresponding traffics in the
respective states in Timetable Period 2016/2017 n Determination of average charges per state according to legal
requirements of § 37 ERegG
n Outlook: Average charges per state in this
market segment will rise by 1,8% p.a.,
starting in Timetable Period 2017/2018 old: new:
8 DB Netz AG | I.NMK2 (T) | 21.09.2017
In local passenger traffic each federal state forms ist
NEW
own market segment for load and empty run
SPNV
Baden-Württemberg Hessen Sachsen Baden-Württemberg Hessen Sachsen
Lastfahrt Lastfahrt Lastfahrt Leerfahrt Leerfahrt Leerfahrt
Mecklenburg- Mecklenburg-
Bayern Sachsen-Anhalt Bayern Sachsen-Anhalt
Vorpommern Vorpommern
Lastfahrt Lastfahrt Leerfahrt Leerfahrt
Lastfahrt Leerfahrt
Berlin Niedersachsen Schleswig-Holstein Berlin Niedersachsen Schleswig-Holstein
Lastfahrt Lastfahrt Lastfahrt Leerfahrt Leerfahrt Leerfahrt
Nordrhein- Nordrhein-
Brandenburg Thüringen Brandenburg Thüringen
Westfalen Westfalen
Lastfahrt Lastfahrt Leerfahrt Leerfahrt
Lastfahrt Leerfahrt
Bremen Rheinland-Pfalz Bremen Rheinland-Pfalz
Leerfahrt
Lastfahrt Lastfahrt Leerfahrt Leerfahrt
Hamburg Saarland Hamburg Saarland
Lastfahrt Lastfahrt Leerfahrt Leerfahrt
9 DB Netz AG | I.NMK2 (T) | 21.09.2017
Local/suburban passenger transport charges
NEW
TAC 2018 – Charges [Euro/Trainkilometer]
Load Load
Empty run Empty run
State Direct costs run State Direct costs run
2018 2018
2018 2018
BW 5,112 NI 5,189
0,666 2,990 0,666 3,375
5,141 5,196
BY 4,983 NRW 4,970
0,666 3,151 0,666 3,340
5,014 5,015
BE 5,413 RP 5,155
0,666 3,290 0,666 3,141
5,419 5,162
BB 5,531 SL 5,279
0,666 3,456 0,666 3,194
5,552 5,272
HB 5,439 SN 5,219
0,666 3,520 0,666 3,199
5,446 5,213
HH 4,778 ST 5,187
0,666 2,884 0,666 3,115
4,776 5,217
HE 4,864 SH 5,285
0,666 2,954 0,666 3,225
4,875 5,288
MV 5,406 TH 5,226
0,666 3,265 0,666 3,180
5,414 5,241
All sates Direct costs Charges 2018
Lok-/ Leerfahrt 0,627 2,46
10 DB Netz AG | I.NMK2 (T) | 21.09.2017
Current issues
11 DB Netz AG | I.NMK2 (T) | 21.09.2017
The regulatory body specified the guidelines of the
National Railway Act to implement the new price cap regulation
Calculation of the price cap in four steps:
1) Base Year: identification of average costs and traffic volumes prior to the control period
– The average is formed by up to 5 past and concluded business years
– DB Netz then identifies the average costs and traffic volumes of these years and the BNetzA checks them
2) AGK: update of base year costs to the starting level of overall costs
– Base year costs are udated to account for developements during the time lag between the base year and the beginning of the control
period, e.g. increasing costs for workforce or quailty requirements
– DB Netz indentifies the updated costs, which are then again checked by the regulatory body
3) OGK: update of the starting level of overall costs to yearly cost caps
– The yearly cost cap accounts for general inflation via an inflation rate and sets an incentive for the track access manager via a
productivity rate
4) Price Cap: division of the yearly cost cap by the base year traffic volume = yearly price cap
inflation rate -
productivity rate
2014 2015 2016 Base Year AGK OGK OGK … OGK
2019 2020 2023
12 DB Netz AG | I.NMK2 (T) | 21.09.2017
Thank you for your attention
PRIME Platform of Rail Infrastructure
Managers in Europe
General Presentation
April 2017
1
Main features
Aims to fulfil the role of the European Network of Infrastructure Managers as foreseen in Article 7f of
Directive (EU) 2016/2370
The only platform allowing direct exchange between IMs and the EC, and co-chaired by both
Allowing discussion of legislative initiatives at a very early stage
Allowing all IMs to cooperate and establish common priorities
Comprehensive scope encompasses all strategic (regulatory, operational and financial) aspects
relevant for IMs
Added value
‘Influencing’ function: industry able to affect draft legislation
‘Early warning’ function: EC to industry and industry to EC
‘Stress-test’ function: EC to test legislative proposals re their ‘implementability‘
‘Learning’ function: EC and IM to improve mutual understanding of respective ‘business’
‘Business’ function: Facilitating benchmarking on best practice to enhance IMs business capabilities
2
The Evolution of PRIME – timeline
September 2013 October 2013 January 2014 March 2014 June 2016 Today
EC proposes First IMs to sign First PRIME meeting, Subgroups on Key 26 participants, 30 participants,
Declaration of the Declaration of working arrangements Performance Indicators 5 subgroups, 5 subgroups, 2
Intent to all IMs to Intent approved and Implementing Acts cooperation with cooperation platforms,
set up PRIME created regulators preparing for the European
ad hoc security group, Network of rail IMs
PRIME PRIME PRIME PRIME
3
Members
As of 1 January 2017, PRIME has the following signatories:
EU IMs Associations
European Commission 1. Adif, ES 13. LISEA, FR 1. CER
2. Banedanmark, DK 14. Lietuvos geležinkeliai, LT 2. EIM
3. BLS Netz AG, CH 15. Network Rail, UK 3. RNE
4. CFR, RO 16. ÖBB Infrastruktur AG, AT 4. VDV
5. DB Netz AG, DE 17. Øresundsbro Konsortiet, DK
6. Eurotunnel, FR/UK 18. PKP PLK, PL
7. FTA, FI 19. ProRail, NL
8. GYSEV, AT/HU 20. RFI, IT
9. Highspeed1, UK 21. SBB, CH
10. Iarnród Éireann – Irish Rail, IE 22. SNCF Réseau, FR
11. Infrabel, BE 23. Trafikverket, SE
12. IP S.A, PT 24. Trasse Schweiz AG, CH
13. Jernbaneverket, NO 25. VPE, HU
4
Plenary meetings (2015 – 2017)
5th February 3rd June 19th November
2015
PRIME, PRIME, PRIME,
5th Meeting 6th Meeting 7th Meeting
Brussels, BE Warsaw, PL Brussels, BE
3rd June 17 November
2016
PRIME, PRIME,
8th Meeting 9th Meeting
Westwood, UK Brussels, BE
12 June 16 November (tbc)
2017
PRIME, PRIME,
10th Meeting 11th Meeting
Sopron, HU Brussels, BE
5
Priorities in 2017
Work in subgroups: Cooperation platforms:
• Twinning programme • Pilot projects for
innovative financing ENRRB (regulators)
Safety Culture • Testing methods for • Dialogue with
/ Occurrence developing and Financing investors
monitoring safety
• Benchmark on
RU Dialogue
reporting culture financing the
maintenance works
• Building information
Strategic discussions:
model • Consultation on
• Simulation and legislative work PRIME 10 – Environmental performance
Digitalisation optimisation Implementing • Input to EC of railways
• Big data acts
PRIME 11 – Rail in multimodal context
• E-catalogue of
projects
• Testing approach Ad hoc topics:
• Collecting data
Performance • First test report
Development of rail infrastructure
Benchmarking • Cooperation with ERMTS
regulators and RUs
Security
6
Governance (as of 1 January 2017)
Signatories: EC, all IMs and associations
Plenary
Co-Chairmenship Mandate of
industry co-chair
unitl June 2017
&
Matthew Baldwin
EC DG MOVE, Alain Quinet
Deputy Director General SNCF Réseau (FR)
Deputy Director General
Subgroups and IMs in lead Cooperation Platforms and IMs in lead
KPI / Benchmarking Trafikverket (SE)
Safety Culture Network Rail (UK) (next - ProRail (NL))
PRIME and ENRBB PKP-PLK (PL)
Implementing Acts RFI (IT)
PRIME and RU Dialogue TBC
Financing EC DG MOVE / SNCF Réseau (FR)
Digital Railways Network Rail (UK)
7
Outlook
► PRIME prepares for becoming a formal European Network of Infrastructure Managers as
foreseen in the 4th Railway Pakcage and all main IMs are expected to join
► PRIME will make recommendations to DG MOVE supporting the development of EU rail
legislation
► PRIME will work closely with the European Commission on IM related topics for the development
of the European rail system
► PRIME members will held targeted strategic discussions, cooperate on priorities and exchange
best practices for IMs becoming more efficient, innovative and responsive to customer needs
8
PRIME key events 2013-2016
1st signing ceremony 2nd signing ceremony PRIME plenary meeting
Host: European Commission Host: EIM Host: ADIF
Tallinn, October 2013 Brussels, November 2014 Madrid, October 2014
PRIME plenary meeting
PRIME plenary meeting PRIME plenary meeting
Host: Network Rail
Host: PKP-PLK Host: European Commission
Westwood Coventry, June 2016
Warsaw, June 2015 Brussels, November 2015
9
Additional information
Legal status of PRIME: registered expert group of the EC
(http://ec.europa.eu/transparency/regexpert/index.cfm?do=groupDetail.groupDetail&groupID=2983)
Legal document of PRIME: Declaration of Intent
(https://webgate.ec.europa.eu/multisite/primeinfrastructure/en/about-prime/description)
Contacts: Alain Quinet Matthew Baldwin
Industry co-chair of PRIME EC co-chair of PRIME
Contact via Paul Mazataud Contact via Annika Kroon
e-mail:
[email protected] [email protected]
PRIME Website : https://webgate.ec.europa.eu/multisite/primeinfrastructure/prime-news_en
10
Public Railway in Estonia 2017
Network overview – Heigo Saare
Charging Methodology – Taavi Laja
Contents
l Railway Infrastructure and market in Estonia
l Legal framework and implementing of new charging
methodology
l Charging principles
l Proposed model
l Discussion / questions
OSJD RULES
Dynamics of passenger and freight trains
2004-2016
4,50 25000
4,00
20000
3,50
3,00
15000
2,50
million
2,00
10000
1,50
1,00
5000
0,50
0,00 0
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
Passenger train (train/km) Freight train (grosstonne/km)
Legal framework and implementing of new
charging methodology
Changes in Railway Law –
requirements of EU 2012/34 Establishing the charging scheme and framewrok by TJA
charging principles (incl. model, prices, units, segments,mark-ups..)
April 2016 September 2016 – June 2017
New metohodology Act by Ministry of Implementing new
Economics and communications (incl. EU charging methodoloy
2015/909 Direct Cost calculation) December 2017
August 2016
Infrastructure charging system
• Deducting the non-eligible from the full costs according to EU
2015/909 (appr. 20% of full costs)
• Including main tracks only
• Cost structure based on cost drivers (weight related costs and
general infrastructure costs)
• Train-km
• Brutotonne-km
• Mandatory level of segmentation + the freight services from
and to 3rd countries
Proposed model (Basic service)
Direct Cost
(Minimum
20-25 %
All segments.
Gross tonne - km / EUR
Train - km / EUR
1
access According to actual
+
package) use
Other (not 2
Passenger train
related with the
minimum access
package)
75-80%
Gross tonne - km / EUR
3
Train - km / EUR
Freight train
Mark-ups (based (segment nr 1)
+
on the specifics of
the segment)
4* Freight train
(segment n)
Lithuanian railways
Lithuanian railway network
Latvia
Klaipėda
1520 mm gauge railway lines
1761 km
Russia
1435 mm gauge railway line Vilnius
(Kaliningrad Kaunas
115 km
region)
Electrified sections Belarus
149 km
Poland
The main freight terminals
The main stakeholders of LT railway transport sector
Railway market regulator
• The Communications Regulatory Authority (from 11/2016)
(till 11/2016 the Competition Council)
Charging & capacity allocation body
• The State Railway Inspectorate
(09/2017 SRI incorporated into the State Road Transport Inspectorate)
Railway infrastructure manager
• JSC „Lithuanian Railways“ Railway infrastructure directorate
Railway undertakings
• JSC „Lithuanian Railways“ Freight transportation directorate
• JSC „Lithuanian Railways“ Passenger transportation directorate
• Companies operating in marshaling yards and sidings
(more than 20 companies)
Dominating freight transportation
2016
Freight – 48 mill. t Passengers – 4.4 mill.
Train kilometers Gross tone-kilometers
4,6%
42,3% 57 95
,7% ,4%
Freight trains Passenger trains Freight trains Passenger trains
Transit from/to 3rd countries
Proportions of rail freight turnover
(2016, tone kilometers)
38,7% 45
,8%
15,5%
Transit through Klaipeda sea port
Transit to/from Kaliningrad region
Other freight (domestic/import/export)
Oil and fertilizers – dominating freight
Proportions of freight transported by
rail
2%(2016, tones)
6% 4%
6%
30%
10%
30%
12%
Oil Fertilizers
Food, grain Mineral products
Metals Coal
Wood Other
Modal share
Freight transportation in
Lithuanian territory – 66% by rail
Source: EUROSTAT – Statistics Explained (2015)
http://ec.europa.eu/eurostat/statistics-explained/
Public financing is close to zero
Financial architecture of Estimated subsidies 2015 (million EUR)
the Lithuanian Railways Infrastructure &
PSO & pensions Total
other aid
Financing of • Almost all costs (losses) of AT -Austria 786 2006 2792
BE-Belgium 1122 1866 2988
passenger passenger transportation are BG-Bulgaria 100 84 184
transportation covered by carrier (state subsidy CZ - Czech Rep 516 0 516
<1% of costs) DE-Germany
DK-Denmark
5131 4585 9716
625 3 628
• Acquisition of all new passenger EE-Estonia 15 27 42
ES-Spain 619 73 692
rolling stock is financed by carrier FI-Finland 106 0 106
only FR- France 8696 3556 12252
EL-Greece 50 333 383
Financing of • 100% of infrastructure operational HR-Croatia 69 563 632
HU-Hungary
railway and renewal costs are covered by IE-Ireland
544 738 1283
98 210 308
infrastructure infrastructure charges IT-Italy 503 2421 2924
LT-Lithuania 3 1 4
• Only development of LU-Luxembourg 359 0 359
infrastructure is financed partially LV-Latvia 32 0 32
NL-Netherlands
by public funds (mostly EU funds) PL-Poland
-175
753
1961
591
1786
1345
PT-Portugal
Other subsidies • Lithuanian railway companies do RO-Romania
18 34 52
329 211 541
for railway not receive any substantial grants SE-Sweden 411 2 413
companies for other purposes SI-Slovenia 46 0 46
SK-Slovakia 218 411 629
Dividends to the • From 2008 (except 2016) JSC UK 963 0 957
Total
State budget “Lithuanian Railways" payed 21938 19677 41611
dividends to the State budget Source: DG Competition
http://ec.europa.eu/competition/state_aid/scoreboard/
Charging scheme in
Lithuania
Railway transport code
Principles on General charging
charging rules procedures
Charging body – Railway
state inspectorate*
Charge for a minimum
access package must be set - sets minimum access charges
on direct cost level and mark-ups’ values
- calculates and sets amounts to
be paid by RU
Mark-ups allowed on: Infrastructure manager – JSC
- passenger and cargo Lithuanian railways (Railway
transit infrastructure directorate)
- transportation segments - uses infrastructure charges to
where market can bear carry out the functions of IM
* From 09/2017 RSI is incorporated into the State
Road Transport Inspectorate
Charges for the minimum access package
• Train traffic charge
gross-tone km
Direct cost
• Use of the contact grid <30%
level charges electric train km
Until 12/2017 – capacity reservation charge;
from new 2017-2018 timetable period eliminated
• Passenger transit charge
gross-tone tkm
• Cargo transit charge
tone km
Mark-ups • Cargo carriage charge
>70%
tone-km
• dangerous goods
• containers, semi-trailers etc.
• low-value goods
• other goods
Regulation 2015/909 implementation
The parts related to use of traction
current and access to infrastructure
Network full cost is calculated
connecting service facilities are
subtracted. =
Eligible costs Network full
cost
Renewal costs added
+ ― Unrelated costs are
(depreciation of some assets
Renewal Six step Unrelated subtracted (costs of
multiplied by CATRIN approach
costs cost providing commercial
elasticity 0,1-0,95 ) services)
NO renewals by EU funds. ―
Unrelated part ―
of maintenance Non eligible
costs costs
Costs that partly related
to train movement Non-eligible costs are
calculated (using CATRIN subtracted
0,2-0,45)
Preliminary result of the new methodology – reduction of the direct
costs level from ~30% to ~20% of all infrastructure costs.
Thank You for attention
Directorate for Railways
Republic of Serbia
SERBIAN RAILWAY SECTOR AND TAC SCHEME
CHRISTINE meeting Jana Ćirković
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Serbian railway sector
§ Strategic transportation location - the easiest route of land travel from continental
Europe to Asia Minor and the Near East.
§ The railway network of the Republic of Serbia is connected with the railway networks of
eight countries: Croatia, Hungary, Romania, Bulgaria, FYR of Macedonia, Montenegro,
Albania and Bosnia and Herzegovina.
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Serbian railway sector
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Serbian railway sector
§ The total length of railway lines – 3.809 km
§ Railways that are part of the Pan-European corridor, railways of the international importance
which connect Serbia with neighboring countries, and local railways
§ About 7.5% of the whole length of the network (275 km) are double-track rail lines
§ 33% of the network - 1.245 km is electrified
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Serbian railway sector
§ Normal gauge of 1435 mm
§ Crossing state borders - no changes in width of gauge
§ Maximum designed speed is 120km/h
§ Museum and touristic railway "Shargan Eight", 21.7 km long, and the track width is 760 mm
§ In respect of the ownership and management of railway infrastructure there is only one railway
network, the state network governed by “Infrastruktura Zeleznice Srbije”
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Corridor X
§ The most important part of the railway network -
Corridor X (Salzburg - Ljubljana - Zagreb -) Sid-
Belgrade - Nis - Presevo (- Skopje - Veles -Solun) with
branches over Subotica (Corridor Xb) on the Hungarian
border and Dimitrovgrad on the Bulgarian border
(Corridor Xc)
§ Total length through Serbia - 875 km
§ Only 20% of the total railway network across Serbia
§ 50% of total rail transport is operated alongside this
route
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Gradual opening of the market
3 stages:
§ The first phase will contribute to the national competition on Serbian railways
§ The second phase will contribute to the regional competition in the SEETO area
§ The third phase will contribute to the opening towards the EU when the international
operators can be expected on the national lines on the basis of reciprocity
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Gradual opening of the market
July 2, 2015 - Government’s decision on the status change of "Zeleznice Srbije", separation with
the establishment of new joint-stock companies:
§ "Zeleznice Srbije plc“ - a technical consulting company with assigned debts
§ "Infrastruktura Zeleznice Srbije" - manages the railway infrastructure of the Republic of
Serbia
§ "Srbija Voz"- transport of passengers
§ “Srbija Kargo"- transport of goods
in accordance with EU regulations as well as with relevant Law of the Republic of Serbia.
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Gradual opening of the market
§ February 2016. - "Infrastruktura Zeleznice Srbije" published its first Network Statement - an
impulse needed for the final opening of Serbian railway market.
§ June 2016. - The first contract on the use of railway infrastructure signed with the railway
undertaking “Kombinovani prevoz”
§ 14 undertakings on the railway market, with a valid license for railway transport.
§ Only one company registered for the carriage of passengers, others are registered for freight
transport.
§ Only five companies have a safety certificate for railway transport issued in accordance with the
new EU regulations, and they include Part A and Part B of the safety certificates.
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Directorate for Railways
§ Established in 2005 by the Law on Railways (‘Official Gazette of RS’, No 18/05, repealed
by No 45/2013), as a special organization of the Republic of Serbia for the field of
railway transport
§ Legal entity
§ MC is appointed by the Government upon the proposal of PM
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Directorate for Railways
Law on Railways adopted in May 2013 ("Official Journal of the RS", No 45/2013, 91/2015)
reinforced the role of the DfR assuming the functions of a:
§ Regulatory body
§ Licensing authority and
§ National safety authority
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Regulatory function
Article 93
DfR decides upon complaints of the applicants for the train path allocation, particularly having in
mind possible unfair conduct or discrimination by the Infrastructure Manager or Railway
Undertakings in relation to the following:
§ Network Statement
§ criteria determined in the Network Statement
§ train path allocation procedure and its outcome
§ manner of determination of the charges for the use of train path
§ levels or structure of the charges for the use of train path
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
TAC scheme
§ Government’s Regulation - methodology for evaluation of the elements for
determining track access charges
§ In line with Regulation 2015/909/EU regarding direct costing principle
§ Further harmonization with new Methodology
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
TAC scheme
§ The subject of the methodology is to evaluate the elements for determining the charge
for the minimum access package and the package for track access to service facilities
and the provision of services in service facilities
§ Based on the principle that carriers only bear the justified costs of IM and costs arising
from the efficient provision of services that users require
§ Based on an economic principle known as marginal cost plus (MT +) - marginal costs
plus added mark up
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
TAC scheme
Marginal costs estimated based on variable costs that include:
§ short-term marginal costs - wear and tear of tracks, management of train traffic and
signaling, fuel consumption and overheads (costs of Timetable planning and the
administrative costs of processing requests for track access)
§ reconstruction costs and financial costs of loan for renewal of the infrastructure
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
TAC scheme
The elements on the basis of which the fee is determined are:
§ category of railway lines (main, regional or local)
§ use of junctions
§ category of train (passenger or freight)
§ type of traction (electric or diesel)
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
TAC scheme
§ Charge’s calculation units are :
1) Train kilometers
2) Gross tone – kilometers
§ TAC scheme is primarily based on the cost allocation model
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Types of services
1) Minimum access package (Category I)
§ Handling of requests for railway infrastructure capacity
§ Use of infrastructure on the main track
§ Train control including signalling, regulations, dispatching, communication systems and
provision of information on train movements
§ Providing all other information necessary for operating the service for which capacity has
been granted
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Types of services
1) Minimum access package (Category I)
§ TAC based directly on the use of infrastructure
§ Consequence of the cost of trains running along the lines.
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Types of services
1) Minimum access package (Category I)
NKI = (ΣVKMijk · CVKMijk) + F · (ΣBRTKMij · CBRTKMij)
§ i – category of railway line
§ j – category of train
§ k - type of traction
§ VKMijk - the number of train kilometers on the network
§ CVKMijk - charge per one train kilometer
§ F - factor depending on the category of the train
§ BRTKMij - number of gross tone-kilometers on the network
§ CBRTKMij – charge per gross tone-kilometer
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Types of services
2) Track access to service facilities (Category IIa) and to the services supplied in these
facilities (Category IIb):
§ passenger stations, their buildings and other facilities
§ freight terminals
§ marshalling yards and train formation facilities, including shunting facilities
§ storage sidings
§ maintenance facilities
§ refuelling facilities
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Types of services
2) Track access to service facilities (Category IIa) and to the services supplied in these
facilities (Category IIb):
§ Services of using the infrastructure capacities in the node as well as the wear of the
tracks when using them
§ On the basis of the ownership
§ Conclusion of separate contract
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
§ l - node
§ m - Category of trains
Types of services §
§
n - Type of traction
Valmn - the number of trains in
the node
2) Track access to service facilities (Category IIa) and to § CValmn - charge per train of
used infrastructure capacity in
the services supplied in these facilities (Category IIb): the node
§ BRTKMlm - the number of gross
NKII = NKIIa + NKIIb tone-kilometers in the node
Track access § CBRTKMlm - charge per gross-
tone kilometer in the node
§ NKIIa = (ΣValmn · CValmn) + (ΣBRTKMlm · CBRTKMlm) § Vblm - number of trains to which
the service is provided (which
Providing of services are "serviced") in the node
§ NKIIb = ΣVblm · CVblm § CVblm – charge per train
"serviced" in the node
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Types of services
3) Additional services (Category III):
§ traction current
§ control of the transport of dangerous goods
§ assistance in the transport of trains with special consignments
§ other additional services
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Types of services
4) Ancillary services (Category IV):
§ Access to telecommunication network
§ Provision of supplementary information
§ Technical inspection of rolling stock
CHRISTINE meeting
Riga, 20-21. September 2017.
Directorate for Railways
Republic of Serbia
Thank you for your attention!
Jana Cirkovic
Directorate for Railways
www.raildir.gov.rs
e-mail:
[email protected]
CHRISTINE meeting
Riga, 20-21. September 2017.
CHRISTINE XI minutes 24 Kugu st. , Riga, Latvia September 20 – 21, 2017 Meeting participants : Stefan Wiedrin ( ÖBB-Infrastruktur AG ) Karl Heinz Codemo ( ÖBB-Infrastruktur AG ) Jessica Tumerelle ( Infrabel ) Sebastien Lejeune ( Infrabel) Dino Džafo ( HŻ Infrastruktura ) Jan Nevola ( SŽDC ) Ladislav Velechovský ( SŽDC ) Bjørn Nielsen Banedanmark ( Hanne ) Réseau Julien Brunel ( SNCF ) Réseau Ferdinand Marterer ( SNCF ) Matthias Fett ( DB-Netz ) Wolfram Merzyn ( DB-Netz ) Giulio Rocco Sitongia ( RFI ) Justina Hudenko ( LatRailNet ) Maris Andiņš ( LatRailNet ) Eriks Pjatkins ( LatRailNet ) Oskars Stūrmanis ( Latvijas Dzelzceļš ) Tatjana Kontijevska ( Latvijas Dzelzceļš ) Adlert Gritter ( Pro Rail ) Julianne Wormsbecher ( Pro Rail ) Pieter van Klaveren ( Pro Rail ) Andrzej Bzdyra ( PLK ) Jaroslaw Wróbel ( PLK ) Ana Salavessa Coutinho ( IP ) Reyes Pinilla ( Adif ) María Álvarez ( Adif ) Pär-Erik Westin ( Trafikverket ) Kjell Kolden ( BAV ) Sigitas Kubilis ( LG ) Martynas Maksimovas ( LG ) Kaur Kajak ( TJA ) Taavi Laja ( TJA ) Heigo Saare ( TJA ) Jana Ćirković ( Diroctorate for Railways ) C hairman of the meeting : J.Hudenko R ecording secretary : E.Pjatkins Day 1: September 20 9:3 0 am - 6:30 pm Introduction part - Presentation of participants and organizational instructions [presented by LatRailNet] - Latvian Railway presentation [presented by Latvijas Dzelzcels] Working session: TAC Differentiation tools - Benchmark TAC 2018 [presented by ÖBB] - Changes in TAC system [presented by HŽ Infrastruktura] - Noise differentiated TAC [presented by BAV] Working session: Market segmentation and mark-ups - Ramsey-Pricing and price elasticities [presented by ÖBB] - Market segmentation and mark-ups in freight [moderated by BAV] : segmentation and mark-up levying approaches differ from country to country. Working session: Factors affecting track maintenance costs - UIC documents usage in cost allocation [presented by ProRail] - Comparative analysis of legal frame and other f actors affecting TAC benchmark [presented by LatRailNet] Day 2: September 21 9:30 am – 2:00 pm : Working session: Other topics and conclusions of CHRISTINE - German TAC system and experience with the regulatory body [presented by DB-Netz] . Discussions: do decisions of regulatory body are binding? - Network area [presented by LatRailNet] CHRISTINE community declines the idea of creating and maintaining web page. - Conclusions of the CHRISTINE session and next venue : the next CHRISTINE meeting will be held at Portugal, Lisbon. All members of CHRISTI N E agree . Discussions: Information exchange among CHRISTINE, PRIME and Commission [moderated by ADIF] : CHRISTINE and PRIME groups have different goals and have to remain as separate working platforms CHRISTINE & PRIME JOINT SESSION: - Presentation of Estonian railway and Charging scheme [presented by TJA] - Presentation of Lithuanian railway and Charging scheme [presented by LG] - Presentation of Serbian railway and Charging scheme [presented by DR] Presentations annexed
Saatja: Ēriks Pjatkins <
[email protected]>
Saaja:
[email protected], Wiederin Stefan (INFRA.Netzzugang),
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected], Rónai Péter, Urvald Krisztián, CIUFFINI FRANCESCA, SITONGIA GIULIO ROCCO, Aldert Gritter,
[email protected],
[email protected],
[email protected], Wróbel Jarosław, Ana C.M.F. Salavessa da Costa Oliveira Coutinho,
[email protected],
[email protected], Álvaro Mascaraque,
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected],
[email protected], Kaur Kajak, Taavi Laja, Heigo Saare,
[email protected], Justina Hudenko
Teema: Minutes and prezentations of 11th CHRISTINE conference.
Dear colleagues,
On behalf of the LatRailNet I would like to thank you once again for
taking part and making presentations at the 11th CHRISTINE meeting!
With the consent of CHRISTINE members who had a presentation at the
CHRISTINE conference, I am sending the meeting minutes with attached
presentations. Speaking of which, would you be so kind as to check the
data from benchmarks in ÖBB-infrastructur presentations, if you find any
wrong data, please inform Wiedrin Stefan.
Presentations are uploaded as one whole pdf file with bookmarks.
Best regards,
Ēriks Pjatkins
Assistant manager
AS "LatRailNet"
E-Mail:
[email protected] <mailto:
[email protected]>
www.ldz.lv <http://www.ldz.lv/>
The information in this e-mail is confidential. The e-mail is intended
solely for the indicated addresse. Mailbody unauthorized disclosure,
distribution or modification is prohibited and may be regarded as an
illegal action. If you are not the recepient of this e-mail, please
inform the sender and delete the e-mail from the system.